TM 11-6130-377-14
e. Remove the electrical leads and diodes A1CRI
k. Close the front indicator panel and secure with
and A1CR2 from the DC circuit breaker A1CB1.
four captive screws.
f. Remove four screws and washers securing the
DC circuit breaker A1CB1 to the front indicator panel
and remove the circuit breaker.
the inverter to check for proper operation of circuit
g. Install the replacement circuit breaker in the
breaker A1CB2.
cutout of the front indicator panel and align the screw
holes.
6-13.
Meter, Indicators A1M1, A1M2, A1M3 and
A1M4
h. Insert the four screws and washers through the
front indicator panel and into the circuit breaker.
All four meters of the inverter are mounted in the same
Tighten the screws to secure the circuit breaker to the
manner. The electrical leads to the meter terminals are
front panel.
different. The same method of removal or replacement
shall be used for all four. To remove or replace a meter
and A1CR2 on the circuit breaker terminals and secure
proceed as follows:
with washers and nuts.
a. Position DC circuit breaker A1CB1 to OFF.
j. Connect the DC input cables to the terminals of
b. Open front indicator panel to gain access to
A1TB1.
meter terminals and hold down clamp.
k. Close the front indicator panel and secure with
c. Tag the electrical leads going to the terminals of
four captive screws.
the meter that requires removing to ensure proper
reassembly.
m. Perform a functional verification (para 6-22) of
d. Remove the electrical leads from the meter
the inverter to check for proper operation of the circuit
terminals and replace the nuts and washers on the
breaker A1CB1.
terminal lugs.
6-12.
AC Circuit Breaker A1CB2
CAUTION
The meter and the bezel must be
To remove or replace the AC circuit breaker A1CB2
supported during the following step
proceed as follows:
to prevent damage.
b. Open the front indicator panel to gain access to
e. Loosen the screws of the two meter clamps and
DC INPUT terminal board A1TB1.
remove the clamps.
c. Disconnect DC input electrical cables from
f. Remove the bezel from the forward side of the
terminal board A1TB1.
indicator panel and the meter from the rear side of the
d. Tag all electrical leads going to the terminals of
indicator panel.
AC circuit breaker A1CB2 to ensure proper reassembly.
g. Install bezel from the front, in cutout of front
e. Remove the screws and washers securing the
indicator panel.
electrical leads to the terminals of the circuit breaker
h. Position meter between the slotted sides of the
A1CB2 and remove the leads.
bezel so that the meter face aligns with the panel cutout
f. Back off the four nuts securing the circuit
and the bezel opening.
breaker brackets to the front panel unit the circuit
i. Insert the securing brackets with screws
breaker can be lifted from the brackets. Remove the
installed through the slots in the side of the bezel and
circuit breaker.
rest them on the frame of the meter.
g. Position replacement circuit breaker in brackets
j. Tighten the screws evenly against the front
and align with cutout in front panel.
panel assembly. This will pull the bezel and meter tight
h. Tighten the four nuts to pull the circuit breaker
against the panel and secure them.
bracket tight against the front panel and circuit breaker.
k. Install the electrical leads to their respective
i. Install the electrical leads on the circuit break
terminals and secure with nuts and washers.
terminals using the screws and washers.
Tighten
l. Close front indicator panel and secure with
screws.
captive screws.
j. Reconnect the DC input electrical cables to the
DC INPUT terminal board A1TB1.
Change 1
6-13
|